U.S. Highway 380 Project
From Collin County Line to FM 903

The Texas Department of Transportation awarded the construction contract for this project in early May to RK Hall.  Construction is scheduled to begin in July and is estimated to take 2 years to complete.  This project is to reconstruct the portion of US 380 that is outside the city limits to a 4 lane divided highway and reconstruct the portion of US 380 that is inside the city limits to a 5 lane (4 lanes with a left turn lane) with curb and gutter.  This project includes the construction of a bridge over the KCS Railroad.


From FM 903 to US 69
The drop inlets and storm sewer along Lee Street are complete.  The bridges at East Caddo Creek and Warren Branch Roadway B are almost complete.

The contractor is installing flexible base for Roadway B and a detour and new location roadway.  Construction of the header banks at the KCS Railroad overpass are underway.

 